BlogBuying and receiving5 min read

A freight claim letter for damaged furniture

Make the claim specific: identify the shipment, state the loss and amount, and attach the evidence. Use this template as the starting point for a covered motor-carrier claim.

The OrderPilot team·

Seen from above, Chip presses a plain document envelope closed beside an orderly stationery table in golden afternoon light.

“Your driver damaged our sofa, please advise” starts a conversation. It does not clearly state a monetary claim. A useful freight claim letter identifies the shipment, explains the loss, states the carrier's asserted responsibility, and requests a supported amount.

For covered U.S. motor-carrier claims, those basics come from 49 CFR § 370.3. Complete the template with the actual shipment facts, remove instructions that do not fit, and send it through the carrier's designated claims process.

General information, not legal advice.

Fill in the claim letter

Date: [date] To: [carrier's claims department and designated submission address] From: [claimant's legal name, address, contact person, telephone, and email] Subject: Freight damage claim — PRO [number], bill of lading [number] We submit a claim against [carrier] for damage to the shipment identified below. [Claimant] is entitled or authorized to make this claim because [state the supported basis and attach authorization if needed]. Shipment: [shipper and origin]; [consignee and destination]; shipped [date]; delivered [date]. Goods: [model, configuration, quantity, carton or serial identifiers, and PO reference]. Damage and circumstances: [describe what was found, where, when, and by whom]. The delivery receipt records [quote the actual exceptions, or state accurately that none were recorded]. Concealed damage was reported on [date], and inspection was requested on [date]. We hold [carrier] liable for this loss because [state the factual basis supported by the shipment and inspection evidence]. Amount claimed: [specific amount and currency]. Calculation: [identify each supported component, quantity, unit amount, and deduction; reconcile to the total]. The goods and packaging are [describe their actual condition and location]. Inspection [is requested / occurred on date / was waived in writing on date]. Attached are [list the documents supplied]. Please acknowledge receipt with the claim number and any additional information required within the period provided by 49 CFR § 370.5. Please direct correspondence to [contact]. [Name and title of authorized signatory]

The letter should be accurate where the facts are inconvenient too. Do not invent a delivery-receipt exception or say packaging is available if it has been discarded.

Attach records that establish the shipment and value

Use this checklist to build the package:

  • Bill of lading and shipment reference.
  • Signed delivery receipt, including recorded exceptions.
  • Photographs of the carton, internal packing, labels, and damaged piece.
  • Vendor invoice showing the actual item and discounts.
  • PO and agreed configuration.
  • Freight bill or other charge evidence.
  • Inspection report or written waiver.
  • Repair estimate, salvage evidence, or written disposition instructions.
  • Claim authorization where someone files on another party's behalf.
  • Earlier damage notice and proof it was sent.

49 CFR § 370.7 identifies supporting documents the investigation can require. A photograph explains condition; an invoice supports value. Neither replaces the written demand.

Name the files by shipment and purpose. In a furniture store, a folder simply called “sofa” has rather a lot of competition.

Show the amount without treating retail price as automatic

Start with the vendor invoice and evidence of the actual loss. The governing measure and any valid liability limitation determine recovery, so neither your retail price nor your purchase cost is automatically the final payable amount.

For a simple illustrative calculation, suppose the supported value is $1,200 and an agreed salvage deduction is $100. The stated claim would be $1,100, with both figures documented. Do not also claim a full replacement and a full repair for the same damage.

Check with your attorney before adding freight, customer-delay costs, lost sales, or other disputed components. 49 U.S.C. § 14706 addresses actual loss or injury to the property; the circumstances and governing terms need to support the demand.

Pull the purchasing evidence from OrderPilot

The PO's receiving history identifies the accepted or rejected unit, the date, and the reason. Its record PDF after receiving can show received quantities and received and landed costs. Keep the vendor invoice alongside it rather than treating the PO alone as conclusive proof of recoverable value. Attach the photographs, transport documents, and carrier correspondence to the PO so another team member can assemble the same file. Use the landed-cost guide to explain cost components, and the vendor-credit routine to reconcile any separate vendor resolution without collecting twice for the same loss.

Preserve inspection evidence and submission proof

If the carrier asks to inspect after a repair, disclose the repair and provide before-and-after photographs, invoices, and any authorization. Do not conceal the changed condition. For a piece not yet repaired, obtain inspection or written disposition instructions before altering the evidence.

Email, a portal, or mail can be appropriate when accepted by the carrier's designated process. Save the complete submitted package, its acknowledgment or delivery proof, and the submission date. Sending only to a sales representative is not a reliable substitute for filing with the proper carrier.

The concealed-damage guide covers early notice and evidence preservation; the receiving checklist helps collect that evidence at arrival.

Calendar the response from carrier receipt

49 CFR § 370.5 requires acknowledgment within 30 days unless the claim is paid or declined in writing within that period. Section 370.9 requires disposition within 120 days or a written explanation of delay, followed by status updates every 60 days while unresolved.

Keep the formal filing and lawsuit deadlines separately. Use the Carmack timeline to set those dates from the governing documents and any written disallowance.

Sources

  1. 49 CFR § 370.3: filing of claims — U.S. Department of Transportation regulation, reproduced by Cornell Legal Information Institute; U.S. federal law as of April 8, 2026.
  2. 49 CFR § 370.5: acknowledgment of claims — U.S. Department of Transportation regulation, reproduced by Cornell Legal Information Institute; U.S. federal law as of April 8, 2026.
  3. 49 CFR § 370.7: investigation of claims — U.S. Department of Transportation regulation, reproduced by Cornell Legal Information Institute; U.S. federal law as of April 8, 2026.
  4. 49 CFR § 370.9: disposition of claims — U.S. Department of Transportation regulation, reproduced by Cornell Legal Information Institute; U.S. federal law as of April 8, 2026.
  5. 49 U.S.C. § 14706: carrier liability — U.S. Code, reproduced by Cornell Legal Information Institute; U.S. federal law as of April 8, 2026.

Give your team the tools they deserve

See what changes when every custom order lives in one place, from the showroom floor to your customer’s front door.